COMMERCIAL KITCHEN & FACTORY VENTILATION — INSTALLATION PROCESS
STEP 1 — Building Consent Plans
You prepare all required plans and documentation for your building consent application.
STEP 2 — Kitchen System / Factory Ventilation Design (PS1)
We produce PS1 Design & Assessment Statements.
For PS1 certification, please contact our engineering partner:
Airflow Engineering Ltd — Graham09 478 9439
graham@airflowengineering.co.nz
STEP 3 — Submit Approved PS1
Once your PS1 has been approved by the Council, please email a copy to: MINGFANS_MOTOR@HOTMAIL.COM
Note: In some cases, a PS2 may also be required. Please confirm with the engineer during the process.
STEP 4 — Quotation & System Design
We will provide you with a detailed quotation for the correct exhaust and ventilation system, fully designed and specified in accordance with your approved PS1 documentation.
STEP 5 — Installation Services
We work with trusted, experienced subcontract installers who can carry out the complete installation on your behalf.
STEP 6 — Installation & PS3 Certification
Upon completion of the installation, our installers will prepare and submit PS3 Code Compliance Certifications to the Council for the completed works.
STEP 7 — Final Inspection (PS4)
In some circumstances, the Council may require a PS4 Independent Engineer’s Review and Report to verify that the installation has been carried out correctly and complies with all relevant standards.